摘要: 五强溪水电站左岸高边坡地质情况复杂,岩体破碎,断层、节理裂隙发育,电站工程曾几度停工,其原因之一须对左岸高边坡整治。复工后经精心设计、施工,使边坡安全度过危险期,蠕变边坡得到综合治理。Abstract: In the region of the high slope of left bank of wuqiangxi hydropower sta-tion, the geological condition is very complicted. the rock fractured,fault, joint and fissure aredeveloped. Tie engineering has stopped severaI times. It is nesessary to treat the high slope of leftbank. Tlrough meticulously design and construction, the slope constrnction safely proceeded. Thecreep slope is comprehensively treated.slope, Creep
-
Key words:
- Hydropower station /
- Comprehensive treatment to high slope /
- Creep