Analysis of Force and Deformation of a Double-row Steel Pipe Pile Cofferdam in a Foundation Pit in a Lake
-
摘要: 为便于施工,位于水域中的基坑工程通常需要施作围堰来保证施工场地干燥,但目前对围堰变形的研究尚不完善。以南昌艾溪湖隧道工程为研究背景,利用Midas GTS NX有限元软件,研究围堰宽度、拉杆位置对双排钢管桩围堰变形规律的影响,并通过将模拟计算结果与实测数据进行对比,验证了模型的合理性。研究结果表明:围堰宽度有一个合适的范围,过小过大均会造成围堰变形过大。在本工程中,围堰合理宽度范围为3.5~4.5 m,围堰宽度的改变对围堰内基坑开挖变形影响较小;综合两侧钢管桩变形来看,拉杆设置在围堰顶部0.8 m处时两侧钢管桩变形较小。Abstract: Cofferdams need to be used to ensure the dry construction site for foundation pit located in water areas. However, the study on cofferdams deformation is still not perfect. Based on the research background of Aixihu Tunnel project in Nanchang, Midas GTS NX finite element software was used to study the influence of cofferdam width and tie bar position on the deformation law of double-row steel pipe pile cofferdam. The model is proved to be correct by comparing the simulation results with the actual measurements. The results show that the cofferdam width has an appropriate range, too small and too large will cause the cofferdam deformation is too large. In this project, the reasonable width of cofferdam should be 3.5~4.5 m. The change of cofferdam width has little influence on the excavation deformation of cofferdam foundation. Considering the deformation of both sides of the steel pipe pile, the deformation of the tie rod is small when it is set at 0.8 m on the top of the cofferdam.
-
Key words:
- double-row steel pipe pile cofferdam /
- deformation /
- HSS model /
- foundation pit
-
表 1 支护结构计算参数
支护结构 γ/(kN·m−3) E/GPa υ 截面形式/mm 临湖侧钢管桩 78.5 210 0.3 $ \phi $630,t=10 临基坑侧钢管桩 78.5 210 0.3 $ \phi $630,t=8 拉杆 78.5 210 0.3 $ \phi $32 地下连续墙 24.8 30 0.2 1000 格构柱 78.5 210 0.3 A=76,t=12 钢筋混凝土横撑 24.8 30 0.2 800×1000 表 2 土层计算参数
地层 γ/(kN∙m−3) E/MPa $ E_{50}^{{\text{ref}}} $/MPa $E_{{\text{oed}}}^{{\text{ref}}}$/MPa $E_{{\text{ur}}}^{{\text{ref}}}$/MPa k/(m·d−1) υ c/kPa $\varphi $/(°) G0/MPa γ0.7 厚度/m 堰芯填土 16.9 10 5 0.3 10 12 粉质黏土 19 10.5 10.5 31.5 0.05 0.32 49 22 47.25 0.0002 5 中砂 19.1 16 16 48 110 0.3 0 30 72 0.0002 5 砾砂 20 32 32 96 110 0.3 0 35 115.2 0.0002 5 圆砾 20 35 35 105 110 0.3 0 36 157.5 0.0002 5 强风化泥质粉砂岩 20.1 200 0.8 0.3 30 37 0.5 中等风化泥质粉砂岩 20.5 2890 0.1 0.29 200 37 19.5 -
[1] 许明博. 水中双排钢管桩夹心土围堰施工技术[J]. 建筑工程技术与设计,2019,(1):1209. [2] 吴留伟,郑国兵,吴 蕾,等. 双排钢板桩围堰在超深厚软土地基中的应用[J]. 水运工程,2018,(3):143-148. doi: 10.3969/j.issn.1002-4972.2018.03.024 [3] 许 亮. 深厚淤泥层地质条件下双排钢板桩围堰有限元分析[J]. 水利规划与设计,2019,(12):131-134. [4] 江 杰,顾倩燕,胡 何,等. 双排钢板桩围堰的冗余度分析[J]. 岩土力学,2015,(S1):518-522. doi: 10.16285/j.rsm.2015.S1.090 [5] 杨 熠. 双排钢板桩围堰结构受力变形及稳定性分析[D]. 南昌: 南昌大学, 2020. [6] 黄 建. 钢板桩围堰体系静、动受力变形特性数值分析[D]. 大连: 大连理工大学, 2008. [7] HWANG W K,KIM H E,CHOI H,et al. Proper regulation of the cutoff system in offshore landfill built on clay ground with double walls[J]. Journal of the Korean Geotechnical Society,2019,35(8):5-15. [8] 付 猛,于 洋,丁德亮,等. 东湖通道工程钢板桩围堰抽水过程数值模拟分析[J]. 施工技术,2014,43(S2):197-200. [9] ZHAO T C, DING W Q, WEI L X, et al. The behavior analysis of a cofferdam constructed by double sheet pile wall above muck [C]// Geoshanghai International Conference Springer, Singapore, 2018. [10] GUI M W,HAN K K. An investigation on a failed double-wall cofferdam during construction[J]. Engineering Failure Analysis,2009,16(1):421-432. doi: 10.1016/j.engfailanal.2008.06.004 [11] MOHAMMOD R A K,JIRO T,HIROKI F,et al. Behavior of double sheet pile wall cofferdam on sand observed in centrifuge tests[J]. International Journal of Physical Modelling in Geotechnics,2001,1(4):1-16. doi: 10.1680/ijpmg.2001.010401 [12] 陈香月,徐光黎,田华通,等. 砂卵石地层中单、双排钢板桩围堰现场水平载荷试验研究[J]. 水文地质工程地质,2017,44(1):91-96, 103. doi: 10.16030/j.cnki.issn.1000-3665.2017.01.14