Foundation Optimization of A Highrise Building in Beijing——Analysis and First Application of Composite Foundation with Cast-in-place Plain Concrete Pile Driven by Auger Rig[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2002, 16(4): 201-204,237.
Citation:
Foundation Optimization of A Highrise Building in Beijing——Analysis and First Application of Composite Foundation with Cast-in-place Plain Concrete Pile Driven by Auger Rig[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2002, 16(4): 201-204,237.
Foundation Optimization of A Highrise Building in Beijing——Analysis and First Application of Composite Foundation with Cast-in-place Plain Concrete Pile Driven by Auger Rig[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2002, 16(4): 201-204,237.
Citation:
Foundation Optimization of A Highrise Building in Beijing——Analysis and First Application of Composite Foundation with Cast-in-place Plain Concrete Pile Driven by Auger Rig[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2002, 16(4): 201-204,237.
Foundation Optimization of A Highrise Building in Beijing——Analysis and First Application of Composite Foundation with Cast-in-place Plain Concrete Pile Driven by Auger Rig
Received Date: 2002-05-22 Available Online:
2021-07-20
Introducing the first application of composite foundation with cast-in-place plain concrete pile driven by auger rig in Beijing, comparing it with prefabricated reinforced concrete piled foundation and other composite foundation,analyzing it from the aspects of economics,technique,construction and project time.