PENG You-jun. Analysis on Geotechnical Engineering Inuestigation Features of the First-phase Project of Wuhan No.2 Subway Line[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2006, 20(6): 303-306,310.
Citation: PENG You-jun. Analysis on Geotechnical Engineering Inuestigation Features of the First-phase Project of Wuhan No.2 Subway Line[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2006, 20(6): 303-306,310.

Analysis on Geotechnical Engineering Inuestigation Features of the First-phase Project of Wuhan No.2 Subway Line

  • Received Date: 2006-09-12
    Available Online: 2021-07-06
  • Through an analysis to the features of the regional geology structure, the engineering geology and the hydrology geology of the first-phase project of Wuhan NO. 2 subway line, the basic content and method is showed for geotechnical engineering investigation to the different method for the subway construction under the different physiognomy unit and the different geological condition. In addition, it is pointed out that the features of subway investigation which is different of the general industry and civil construction investigation in aspects on location condition, investigation request and test content. The investigation implementation can be plan reasonably according to these featuers.

     

  • loading
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (58) PDF downloads(7) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return