Wang Caikou, Huang Tao, Chang Wei, Wang Haiyuan, Pu Shikun, Zhai Yongyong. Influence of New Pier Construction on Adjacent Existing High Speed Railway Pier Foundation[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2024, 38(6): 704-711. doi: 10.3969/j.issn.1007-2993.2024.06.010
Citation: Wang Caikou, Huang Tao, Chang Wei, Wang Haiyuan, Pu Shikun, Zhai Yongyong. Influence of New Pier Construction on Adjacent Existing High Speed Railway Pier Foundation[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2024, 38(6): 704-711. doi: 10.3969/j.issn.1007-2993.2024.06.010

Influence of New Pier Construction on Adjacent Existing High Speed Railway Pier Foundation

doi: 10.3969/j.issn.1007-2993.2024.06.010
  • Received Date: 2023-11-16
  • Accepted Date: 2024-05-09
  • Rev Recd Date: 2024-04-18
  • Publish Date: 2024-12-06
  • To study the influence of new pier construction on adjacent high-speed rail pier foundation, the whole construction process calculation model of the new pier was established based on the hardening soil model with small-strain stiffness (HSS model) and PLAXIS 3D finite element software, and then the soil displacement characteristics of adjacent existing high-speed rail pier foundation were analyzed. The reliability of the finite element model was verified by compared with the field monitoring data. The displacement of the pier and pile was calculated and analyzed. The results show that the HSS model is helpful to obtain more reliable displacement results in finite element calculation. In terms of soil mass, the maximum horizontal displacement and settlement are 1.53 mm and 5.49 mm in the horizontal direction of the foundation pit. The maximum settlement of the existing pier and cap is less than 6 mm, and the total settlement of the pier cap and the differential settlement of the adjacent pier cap is less than the standard limit. The outer top of the pile group of the existing pile foundation has a displacement to the four sides, while the top of the middle pile has a small settlement and bears the "open pattern" displacement state. During the construction of the new pier, the construction of the new bored pile, the insertion of the steel sheet pile, and the backfilling of the foundation pit have a great influence on the horizontal displacement and settlement of the existing high-speed railway pier foundation.

     

  • loading
  • [1]
    于建勇. 新建常州至泰州城际铁路必要性研究[J]. 交通工程,2020,20(2):60-64,72.
    [2]
    张 旭, 王杰杰. 深基坑施工对邻近既有地铁车站附属的影响分析[J]. 岩土工程技术,2023,37(4):492-498. doi: 10.3969/j.issn.1007-2993.2023.04.021
    [3]
    周志良, 仇 欢, 黄晓东, 等. 钻孔灌注桩施工对邻近运营隧道变形影响研究[J]. 岩土工程技术,2021,35(1):1-6,11.
    [4]
    LIYANAPATHIRANA D S, NISHANTHAN R. Influence of deep excavation induced ground movements on adjacent piles[J]. Tunnelling and Underground Space Technology,2016,52(2):168-181. doi: 10.1016/j.tust.2015.11.019
    [5]
    KORFF M, MAIR R J, Van TOL F A F. Pile-soil interaction and settlement effects induced by deep excavations[J]. Journal of Geotechnical and Geoenvironmental Engineering,2016,142(8):04016034. doi: 10.1061/(ASCE)GT.1943-5606.0001434
    [6]
    徐 俊. 深基坑开挖对邻近高速铁路路基影响研究[J]. 铁道建筑技术,2020(10):42-45,88. doi: 10.3969/j.issn.1009-4539.2020.10.010
    [7]
    侯兰新. 深厚软土地基堆载预压对邻近桥梁桩基影响分析[J]. 铁道建筑技术,2022(6):140-144. doi: 10.3969/j.issn.1009-4539.2022.06.031
    [8]
    方淑君, 张利勇, 刘神斌, 等. 新建桥运营状态下对邻近高铁桥基础水平变形的影响分析[J]. 铁道科学与工程学报,2021,18(9):2234-2243.
    [9]
    方淑君, 徐新桐, 王 涛, 等. 运营状态下新建桥对邻近高铁桥梁沉降的分析[J]. 铁道科学与工程学报,2022,19(5):1187-1195.
    [10]
    刘 鑫, 张思卿, 龚天昊, 等. 新建墩承台施工对邻近既有高铁线路基的影响研究[J]. 水利与建筑工程学报,2023,21(2):220-228. doi: 10.3969/j.issn.1672-1144.2023.02.033
    [11]
    岳齐贤, 赵建立, 沈水龙. 泥岩地区沉井施工对土体及高铁桥基影响研究[J]. 地下空间与工程学报,2014,10(4):878-883.
    [12]
    梅 祯, 肖军华, 王炳龙. 基坑开挖对临近基坑地铁高架结构变形的影响[J]. 土木与环境工程学报(中英文),2019,41(4):51-58.
    [13]
    范剑雄, 王海峰, 陕 耀. 新建连镇铁路施工对邻近沪宁城际铁路的影响[J]. 铁道建筑,2022,62(9):136-140. doi: 10.3969/j.issn.1003-1995.2022.09.28
    [14]
    Q/CR 9230—2016 铁路工程沉降变形观测与评估技术规程 [S]. 北京:中国铁道出版社, 2016.
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Figures(9)  / Tables(6)

    Article Metrics

    Article views (71) PDF downloads(15) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return