Volume 40 Issue 3
Jun.  2026
Turn off MathJax
Article Contents
ZHANG Ning. Optimum design of front-braced grouting steel pipe system in the foundation pit engineering in Shanghai[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2026, 40(3): 328-335. doi: 10.20265/j.cnki.issn.1007-2993.2025-0002
Citation: ZHANG Ning. Optimum design of front-braced grouting steel pipe system in the foundation pit engineering in Shanghai[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2026, 40(3): 328-335. doi: 10.20265/j.cnki.issn.1007-2993.2025-0002

Optimum design of front-braced grouting steel pipe system in the foundation pit engineering in Shanghai

doi: 10.20265/j.cnki.issn.1007-2993.2025-0002
  • Received Date: 2025-01-02
  • Accepted Date: 2025-08-25
  • Rev Recd Date: 2025-06-18
  • Available Online: 2026-06-08
  • Publish Date: 2026-06-08
  • Through comparative analysis of the code-calculated and measured deformation characteristics of the front-braced grouting steel pipe system under different geological conditions in Shanghai, optimized design methods and measures for improving bearing capacity and controlling the deformation of retaining piles are proposed and verified by numerical simulation. The results show that: (1) For foundation pits with poor soil conditions at both the pit bottom and the front-braced pile bottom, the measured deformation of the retaining system is significantly larger than the code-calculated value. The optimal horizontal angle of the front-braced piles is 45°. Zoned excavation and the addition of precast cushions during construction can reduce the total deformation of retaining piles by approximately 10%. Further deformation control can be achieved by reducing the single excavation area. (2) For foundation pits with poor soil at the pit bottom but good soil at the front-braced pile bottom, the measured deformation of retaining piles is slightly larger than the code-calculated value. The horizontal angle of front-braced piles can be increased to 50°~55°, which shortens the pile length while maintaining the same horizontal bearing capacity, thus improving economic efficiency. Deformation can be controlled via zoned excavation and cushion installation, and attention should be paid to the shear design between retaining piles and wales. (3) For foundation pits with good soil at both the pit bottom and the front-braced pile bottom, the measured deformation of retaining piles is close to the code-calculated value. The horizontal angle of front-braced piles can be reduced to 30°~35°, which shortens the pile length under constant horizontal bearing capacity, controls the deformation of the pile top, and also improves economic efficiency.

     

  • loading
  • [1]
    上海市建设协会. 自稳式基坑支护结构技术标准: T/SCDA 012—2021[S]. 上海: 上海市建设协会, 2021. (Shanghai Construction & Development Association. Technical standard for self-stable retaining structure of foundation excavation: T/SCDA 012—2021[S]. Shanghai: Shanghai Construction & Development Association, 2021. (in Chinese)

    Shanghai Construction & Development Association. Technical standard for self-stable retaining structure of foundation excavation: T/SCDA 012—2021[S]. Shanghai: Shanghai Construction & Development Association, 2021. (in Chinese)
    [2]
    顾国荣, 杨石飞, 许 杰, 等. 一种可回收直立式钢管前撑围护结构及其应用方法: CN103410156B[P]. 2016-01-27. (GU G R, YANG S F, XU J, et al. Recyclable vertical steel tube front supporting envelop enclosure and applying method thereof: CN103410156B[P]. 2016-01-27. (in Chinese)

    GU G R, YANG S F, XU J, et al. Recyclable vertical steel tube front supporting envelop enclosure and applying method thereof: CN103410156B[P]. 2016-01-27. (in Chinese)
    [3]
    陆秋平, 周 吉, 陆陈华. 前撑式注浆钢管桩在砂质粉土层中的应用[J]. 建筑施工, 2019, 41(10): 1792-1794. (LU Q P, ZHOU J, LU C H. Application of front-braced grouting steel pipe pile in sandy silt layer[J]. Building Construction, 2019, 41(10): 1792-1794. (in Chinese) doi: 10.14144/j.cnki.jzsg.2019.10.005

    LU Q P, ZHOU J, LU C H. Application of front-braced grouting steel pipe pile in sandy silt layer[J]. Building Construction, 2019, 41(10): 1792-1794. (in Chinese) doi: 10.14144/j.cnki.jzsg.2019.10.005
    [4]
    董林兵. 前撑注浆钢管桩在大面积深基坑工程中的应用[J]. 建筑施工, 2020, 42(7): 1126-1127,1137. (DONG L B. Application of steel pipe pile with front support grouting in large area deep foundation pit engineering[J]. Building Construction, 2020, 42(7): 1126-1127,1137. (in Chinese) doi: 10.14144/j.cnki.jzsg.2020.07.005

    DONG L B. Application of steel pipe pile with front support grouting in large area deep foundation pit engineering[J]. Building Construction, 2020, 42(7): 1126-1127,1137. (in Chinese) doi: 10.14144/j.cnki.jzsg.2020.07.005
    [5]
    郑先元, 张 志. 前撑式注浆钢管斜撑体系在基坑工程中的应用分析[J]. 工程质量, 2019, 37(1): 69-72,86. (ZHENG X Y, ZHANG Z. Analysis of application of the advanced grouting steel pipe diagonal brace system in deep foundation excavation engineering[J]. Construction Quality, 2019, 37(1): 69-72,86. (in Chinese) doi: 10.3969/j.issn.1671-3702.2019.01.016

    ZHENG X Y, ZHANG Z. Analysis of application of the advanced grouting steel pipe diagonal brace system in deep foundation excavation engineering[J]. Construction Quality, 2019, 37(1): 69-72,86. (in Chinese) doi: 10.3969/j.issn.1671-3702.2019.01.016
    [6]
    惠彬永. 前撑式注浆钢管支撑在基坑围护中的应用与研究[J]. 建筑施工, 2018, 40(11): 1868-1870. (HUI B Y. Application and research on supporting of front supported type grouting steel pipe in foundation pit support[J]. Building Construction, 2018, 40(11): 1868-1870. (in Chinese) doi: 10.14144/j.cnki.jzsg.2018.11.005

    HUI B Y. Application and research on supporting of front supported type grouting steel pipe in foundation pit support[J]. Building Construction, 2018, 40(11): 1868-1870. (in Chinese) doi: 10.14144/j.cnki.jzsg.2018.11.005
    [7]
    施春锋. 前撑式注浆管在深基坑工程中的应用[J]. 建筑施工, 2022, 44(6): 1157-1159. (SHI C F. Application of front support grouting pipe in deep foundation pit engineering[J]. Building Construction, 2022, 44(6): 1157-1159. (in Chinese) doi: 10.14144/j.cnki.jzsg.2022.06.003

    SHI C F. Application of front support grouting pipe in deep foundation pit engineering[J]. Building Construction, 2022, 44(6): 1157-1159. (in Chinese) doi: 10.14144/j.cnki.jzsg.2022.06.003
    [8]
    徐 枫. 自稳式注浆钢管前撑技术在深大基坑中的应用[J]. 工程勘察, 2024, 52(11): 32-38. (XU F. Application of self stabilizing grouting steel pipe front support technique in deep and large excavations[J]. Geotechnical Investigation & Surveying, 2024, 52(11): 32-38. (in Chinese)

    XU F. Application of self stabilizing grouting steel pipe front support technique in deep and large excavations[J]. Geotechnical Investigation & Surveying, 2024, 52(11): 32-38. (in Chinese)
    [9]
    魏建华, 韩鹏飞, 孔令荣,等 . 双排桩门架结合前撑注浆钢管支护结构在软土深基坑工程中的应用[J]. 地基处理, 2025, 7(3): 303-310. (WEI J H, HAN P F , KONG L R, et al. Application of double-row pile gantry combined with front-supported grouted steel pipe retaining structure in soft soil deep excavation[J]. Journal of Ground Improvement, 2025, 7(3): 303-310. (in Chinese)

    WEI J H, HAN P F , KONG L R, et al. Application of double-row pile gantry combined with front-supported grouted steel pipe retaining structure in soft soil deep excavation[J]. Journal of Ground Improvement, 2025, 7(3): 303-310.
    [10]
    窦红瑞. 自稳式支护技术在基坑工程中的应用[J]. 地基处理, 2025, 7(1): 90-100. (DOU H R. Application of self-stabilizing support technology in foundation pit engineering[J]. Journal of Ground Improvement, 2025, 7(1): 90-100. (in Chinese)

    DOU H R. Application of self-stabilizing support technology in foundation pit engineering[J]. Journal of Ground Improvement, 2025, 7(1): 90-100. (in Chinese)
    [11]
    海明雷, 魏建华. 前撑注浆钢管在某超大软土基坑中的应用[J]. 工程勘察, 2024, 52(3): 24-28. (HAI M L, WEI J H. Application of front-braced grouting steel pipe support in a super large deep excavation in soft ground[J]. Geotechnical Investigation & Surveying, 2024, 52(3): 24-28. (in Chinese)

    HAI M L, WEI J H. Application of front-braced grouting steel pipe support in a super large deep excavation in soft ground[J]. Geotechnical Investigation & Surveying, 2024, 52(3): 24-28. (in Chinese)
    [12]
    李 明. 前撑式注浆钢管桩在软土地区基坑工程中的应用[J]. 建筑施工, 2025, 45(5): 849-851. (LI M. Application of front-supported grouting steel pipe pile in foundation pit engineering in soft soil area[J]. Building Constrction, 2025, 45(5): 849-851. (in Chinese) doi: 10.14144/j.cnki.jzsg.2023.05.007

    LI M. Application of front-supported grouting steel pipe pile in foundation pit engineering in soft soil area[J]. Building Constrction, 2025, 45(5): 849-851. doi: 10.14144/j.cnki.jzsg.2023.05.007
    [13]
    张荣文. 前撑式抗压注浆钢管支撑在基坑支护中的应用[J]. 建筑科技, 2019, 3(3): 128-130. (ZHANG R W. Application of pressure grounting front support in foundation construction[J]. Building Technology, 2019, 3(3): 128-130. (in Chinese) doi: 10.3969/j.issn.1007-046X.2019.03.039

    ZHANG R W. Application of pressure grounting front support in foundation construction[J]. Building Technology, 2019, 3(3): 128-130. (in Chinese) doi: 10.3969/j.issn.1007-046X.2019.03.039
    [14]
    倪浩群. 前撑注浆钢管在软土基坑中的应用[J]. 建筑科技, 2025, 9(3): 80-82,96. (NI H Q. Application of front-bracing grouting steel pipes in soft soil foundation pits[J]. Building Technology, 2025, 9(3): 80-82,96. (in Chinese) doi: 10.3969/j.issn.1007-046X.2025.03.022

    NI H Q. Application of front-bracing grouting steel pipes in soft soil foundation pits[J]. Building Technology, 2025, 9(3): 80-82,96. (in Chinese) doi: 10.3969/j.issn.1007-046X.2025.03.022
    [15]
    霍红伟, 潘昌盛, 蓬金高, 等. 基于前撑注浆钢管支撑体系的基坑施工效率提升研究[J]. 建筑施工, 2023, 45(11): 2157-2159. (HUO H W, PAN C S, PENG J G, et al. Research on improvement of foundation pit construction efficiency based on front support grouting steel pipe support system[J]. Building Construction, 2023, 45(11): 2157-2159. (in Chinese) doi: 10.14144/j.cnki.jzsg.2023.11.001

    HUO H W, PAN C S, PENG J G, et al. Research on improvement of foundation pit construction efficiency based on front support grouting steel pipe support system[J]. Building Construction, 2023, 45(11): 2157-2159. (in Chinese) doi: 10.14144/j.cnki.jzsg.2023.11.001
    [16]
    陈学成. 前撑注浆钢管支护体系在基坑工程中的应用[J]. 广东土木与建筑, 2021, 28(5): 62-64,111. (CHEN X C. Analysis of front-braced grouting steel pipe pile in deep foundation excavation engineering[J]. Guangdong Architecture Civil Engineering, 2021, 28(5): 62-64,111. (in Chinese) doi: 10.3969/j.issn.1007-4104.2025.10.033

    CHEN X C. Analysis of front-braced grouting steel pipe pile in deep foundation excavation engineering[J]. Guangdong Architecture Civil Engineering, 2021, 28(5): 62-64,111. doi: 10.3969/j.issn.1007-4104.2025.10.033
    [17]
    陈海涛, 王 伟, 李 伟, 等. 超前注浆端承钢斜撑在基坑工程中的应用[J]. 建筑施工, 2017, 39(9): 1335-1336,1342. (CHEN H T, WANG W, LI W, et al. Application of advanced grouting at end bearing steel inclined strut to foundation pit engineering[J]. Building Construction, 2017, 39(9): 1335-1336,1342. (in Chinese)

    CHEN H T, WANG W, LI W, et al. Application of advanced grouting at end bearing steel inclined strut to foundation pit engineering[J]. Building Construction, 2017, 39(9): 1335-1336,1342. (in Chinese)
    [18]
    孙锦剑. 前撑注浆钢管桩在地下两层基坑工程中的应用[J]. 广东土木与建筑, 2024, 31(6): 69-71. (SUN J J. Application of pre-braced grouting steel pipe pile in two-storey underground foundation pit engineering[J]. Guangdong Architecture Civil Engineering, 2024, 31(6): 69-71. (in Chinese) doi: 10.19731/j.gdtmyjz.2024.06.015

    SUN J J. Application of pre-braced grouting steel pipe pile in two-storey underground foundation pit engineering[J]. Guangdong Architecture Civil Engineering, 2024, 31(6): 69-71. (in Chinese) doi: 10.19731/j.gdtmyjz.2024.06.015
    [19]
    戴生良, 张 宁, 黄惟奕, 等. 上海地区不同地质条件自稳式斜撑体系变形特性对比分析[J]. 建筑施工, 2022, 44(10): 2312-2315. (DAI S L, ZHANG N, HUANG W Y, et al. Comparative analysis of deformation characteristics of self-stabilizing inclined strut systems under different geological conditions in Shanghai Area[J]. Building Construction, 2022, 44(10): 2312-2315. (in Chinese) doi: 10.14144/j.cnki.jzsg.2022.10.010

    DAI S L, ZHANG N, HUANG W Y, et al. Comparative analysis of deformation characteristics of self-stabilizing inclined strut systems under different geological conditions in Shanghai Area[J]. Building Construction, 2022, 44(10): 2312-2315. (in Chinese) doi: 10.14144/j.cnki.jzsg.2022.10.010
    [20]
    王卫东, 王浩然, 徐中华. 上海地区基坑开挖数值分析中土体HS-Small模型参数的研究[J]. 岩土力学, 2013, 34(6): 1766-1774. (WANG W D, WANG H R, XU Z H. Study of parameters of HS-Small model used in numerical analysis of excavations in Shanghai area[J]. Rock and Soil Mechanics, 2013, 34(6): 1766-1774. (in Chinese)

    WANG W D, WANG H R, XU Z H. Study of parameters of HS-Small model used in numerical analysis of excavations in Shanghai area[J]. Rock and Soil Mechanics, 2013, 34(6): 1766-1774. (in Chinese)
    [21]
    王卫东, 李 青, 徐中华. 软土地层邻近隧道深基坑变形控制设计分析与实践[J]. 隧道建设(中英文), 2022, 42(2): 163-175. (WANG W D, LI Q, XU Z H. Design and application of deformation control techniques for deep foundation pits adjacent to existing tunnels in soft soil[J]. Tunnel Construction, 2022, 42(2): 163-175. (in Chinese) doi: 10.3973/j.issn.2096-4498.2022.02.001

    WANG W D, LI Q, XU Z H. Design and application of deformation control techniques for deep foundation pits adjacent to existing tunnels in soft soil[J]. Tunnel Construction, 2022, 42(2): 163-175. (in Chinese) doi: 10.3973/j.issn.2096-4498.2022.02.001
    [22]
    宗露丹, 徐中华, 翁其平, 等. 小应变本构模型在超深大基坑分析中的应用[J]. 地下空间与工程学报, 2019, 15(S1): 231-242. (ZONG L D, XU Z H, WENG Q P, et al. Application of small strain constitutive model in the analysis of a ultra large and deep excavation[J]. Chinese Journal of Underground Space and Engineering, 2019, 15(S1): 231-242. (in Chinese) doi: 10.20174/j.juse.2019.s1.035

    ZONG L D, XU Z H, WENG Q P, et al. Application of small strain constitutive model in the analysis of a ultra large and deep excavation[J]. Chinese Journal of Underground Space and Engineering, 2019, 15(S1): 231-242. (in Chinese) doi: 10.20174/j.juse.2019.s1.035
    [23]
    孙海忠, 邓捷程. 基于HS-Small模型软土基坑开挖过程三维数值分析[J]. 建筑施工, 2022, 44(6): 1373-1376. (SUN H Z, DENG J C. 3D numerical analysis of soft soil foundation pit excavation process based on HS-Small model[J]. Building Construction, 2022, 44(6): 1373-1376. (in Chinese) doi: 10.14144/j.cnki.jzsg.2022.06.062

    SUN H Z, DENG J C. 3D numerical analysis of soft soil foundation pit excavation process based on HS-Small model[J]. Building Construction, 2022, 44(6): 1373-1376. (in Chinese) doi: 10.14144/j.cnki.jzsg.2022.06.062
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Figures(8)  / Tables(3)

    Article Metrics

    Article views (65) PDF downloads(17) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return