Volume 40 Issue 2
Apr.  2026
Turn off MathJax
Article Contents
CHEN Jia, YU You, YANG Ping, ZHU Jun, WANG Jiahui, FAN Shaowei. Grouting isolation and reinforcement test and measurement analysis of the parallel existing operating line of the overlapping tunnel[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2026, 40(2): 306-316. doi: 10.20265/j.cnki.issn.1007-2993.2025-0068
Citation: CHEN Jia, YU You, YANG Ping, ZHU Jun, WANG Jiahui, FAN Shaowei. Grouting isolation and reinforcement test and measurement analysis of the parallel existing operating line of the overlapping tunnel[J]. GEOTECHNICAL ENGINEERING TECHNIQUE, 2026, 40(2): 306-316. doi: 10.20265/j.cnki.issn.1007-2993.2025-0068

Grouting isolation and reinforcement test and measurement analysis of the parallel existing operating line of the overlapping tunnel

doi: 10.20265/j.cnki.issn.1007-2993.2025-0068
  • Received Date: 2025-02-18
  • Accepted Date: 2025-08-25
  • Rev Recd Date: 2025-07-23
  • Publish Date: 2026-04-09
  • To verify the feasibility of ensuring the safe operation of the existing tunnel by applying the grouting reinforcement isolation wall method in the small-clearance, long parallel section between Nanjing Metro Line 6 and the existing Line 4, a representative test area was selected based on similar stratum distribution. Studies and tests were conducted on the reinforcement method, including grouting process and mix ratio optimization, in-situ deep soil grouting, coring inspection and water injection tests, saturated uniaxial compressive strength tests, as well as earth pressure and deep soil horizontal displacement monitoring. The results indicate that for the strata in this project, it is advisable to employ bentonite-cement slurry and rapid-setting high-strength cement-based slurry. The grouting operation should adopt the methods of "skip-hole drilling" and "cyclic grouting in intervals", with staged grouting for formations at different depths. The lateral reinforcement extent of the grouted zone reaches ≥2.70 m, which can serve as the control criterion for formal grouting construction. During grouting, the earth pressure induced at the equivalent horizontal distance from the existing line was 0.508 MPa, slightly exceeding the design requirement. However, the maximum horizontal displacement of the soil was 4.64 mm, satisfying the design requirements. After grouting reinforcement, the stratum changed from extremely fragmented to moderately complete to relatively complete, and from medium permeable stratum to slightly permeable stratum, and the saturated uniaxial compressive strength of the core samples taken from the inspection hole is more than 1 MPa. Therefore, it is feasible to use this grouting process and parameters for the grouting isolation and reinforcement construction near the existing operating lines. This can provide a reference for the grouting isolation and reinforcement under similar working conditions.

     

  • loading
  • [1]
    李 雪, 龚子邦, 张玉申, 等. 砂卵石地层重叠盾构隧道掘进加固方案比选研究[J]. 现代隧道技术, 2022, 59(S1): 918-927. (LI X, GONG Z B, ZHANG Y S, et al. Comparison and study of reinforcement measures for overlapping shield tunnelling in sandy cobble stratum[J]. Modern Tunnelling Technology, 2022, 59(S1): 918-927. (in Chinese)

    LI X, GONG Z B, ZHANG Y S, et al. Comparison and study of reinforcement measures for overlapping shield tunnelling in sandy cobble stratum[J]. Modern Tunnelling Technology, 2022, 59(S1): 918-927. (in Chinese)
    [2]
    安建永, 雷海波, 尹鸿威, 等. 富水砂层超小净距叠线盾构隧道施工安全控制技术[J]. 隧道建设(中英文), 2021, 41(S2): 503-511. (AN J Y, LEI H B, YIN H W, et al. Safety control technology for ultra-small clear distance overlapping shield tunnel construction in water-rich sandy stratum[J]. Tunnel Construction, 2021, 41(S2): 503-511. (in Chinese)

    AN J Y, LEI H B, YIN H W, et al. Safety control technology for ultra-small clear distance overlapping shield tunnel construction in water-rich sandy stratum[J]. Tunnel Construction, 2021, 41(S2): 503-511. (in Chinese)
    [3]
    黄海龙, 马金骥, 唐 亮, 等. 富水砂层叠落区间盾构扰动控制方案优选[J]. 施工技术(中英文), 2024, 53(13): 6-12,42. (HUANG H L, MA J J, TANG L, et al. Optimization of shield disturbance control scheme in water-rich sand layer overlapping interval[J]. Construction Technology, 2024, 53(13): 6-12,42. (in Chinese)

    HUANG H L, MA J J, TANG L, et al. Optimization of shield disturbance control scheme in water-rich sand layer overlapping interval[J]. Construction Technology, 2024, 53(13): 6-12,42. (in Chinese)
    [4]
    黄大维, 赵梽錡, 徐长节, 等. 侧部注浆对已建盾构隧道受荷变形影响试验研究[J]. 岩土工程学报, 2024, 46(3): 510-518. (HUANG D W, ZHAO Z Q, XU C J, et al. Experimental study on influences of side grouting on deformation of shield tunnels under loads[J]. Chinese Journal of Geotechnical Engineering, 2024, 46(3): 510-518. (in Chinese)

    HUANG D W, ZHAO Z Q, XU C J, et al. Experimental study on influences of side grouting on deformation of shield tunnels under loads[J]. Chinese Journal of Geotechnical Engineering, 2024, 46(3): 510-518. (in Chinese)
    [5]
    LU C R, ZHANG X H, SHI B B, et al. Deformation in settlement and grouting remediation of thickened larger-diameter metro shield tunnel in soft soil: a case study[J]. Case Studies in Construction Materials, 2024, 20: e02736. doi: 10.1016/j.cscm.2023.e02736
    [6]
    丁 程, 程姿洋, 王文恺, 等. 软弱局部透水地层注浆止水盾尾刷更换技术[J]. 林业工程学报, 2024, 9(2): 160-166. (DING C, CHENG Z Y, WANG W K, et al. Study on the replacement technology of shield tail brush by grouting for water plugging in weak and locally permeable stratum[J]. Journal of Forestry Engineering, 2024, 9(2): 160-166. (in Chinese)

    DING C, CHENG Z Y, WANG W K, et al. Study on the replacement technology of shield tail brush by grouting for water plugging in weak and locally permeable stratum[J]. Journal of Forestry Engineering, 2024, 9(2): 160-166. (in Chinese)
    [7]
    邓皇适, 傅鹤林, 史 越, 等. 盾构隧道曲线段掘进引发邻近地下管线变形分析[J]. 中南大学学报(自然科学版), 2022, 53(8): 3008-3020. (DENG H S, FU H L, SHI Y, et al. Research on deformation of adjacent underground pipelines caused by shield machine tunneling along curve section[J]. Journal of Central South University (Science and Technology), 2022, 53(8): 3008-3020. (in Chinese)

    DENG H S, FU H L, SHI Y, et al. Research on deformation of adjacent underground pipelines caused by shield machine tunneling along curve section[J]. Journal of Central South University (Science and Technology), 2022, 53(8): 3008-3020. (in Chinese)
    [8]
    江 杰, 龙逸航, 欧孝夺, 等. 新建曲线地铁盾构隧道下穿施工引起的既有隧道沉降分析[J]. 工程科学与技术, 2023, 55(1): 313-324. (JIANG J, LONG Y H, OU X D, et al. Analysis of existing tunnel settlement caused by undercrossing construction of curved metro shield tunnel[J]. Advanced Engineering Sciences, 2023, 55(1): 313-324. (in Chinese)

    JIANG J, LONG Y H, OU X D, et al. Analysis of existing tunnel settlement caused by undercrossing construction of curved metro shield tunnel[J]. Advanced Engineering Sciences, 2023, 55(1): 313-324. (in Chinese)
    [9]
    江 杰, 龙逸航, 邢轩伟, 等. 富水圆砾地层盾构下穿既有地铁隧道掘进参数研究[J]. 铁道科学与工程学报, 2021, 18(7): 1828-1836. (JIANG J, LONG Y H, XING X W, et al. Study of boring parameters of shield tunnel under traversing existing metro tunnels in water-soaked round gravel strata[J]. Journal of Railway Science and Engineering, 2021, 18(7): 1828-1836. (in Chinese)

    JIANG J, LONG Y H, XING X W, et al. Study of boring parameters of shield tunnel under traversing existing metro tunnels in water-soaked round gravel strata[J]. Journal of Railway Science and Engineering, 2021, 18(7): 1828-1836. (in Chinese)
    [10]
    应宏伟, 姚 言, 王奎华, 等. 双线平行顶管上跨地铁盾构隧道施工环境影响实测分析[J]. 上海交通大学学报, 2023, 57(12): 1639-1647. (YING H W, YAO Y, WANG K H, et al. Observed environment response caused by construction of double-line parallel pipe jacking crossing over metro shield tunnels[J]. Journal of Shanghai Jiao Tong University, 2023, 57(12): 1639-1647. (in Chinese)

    YING H W, YAO Y, WANG K H, et al. Observed environment response caused by construction of double-line parallel pipe jacking crossing over metro shield tunnels[J]. Journal of Shanghai Jiao Tong University, 2023, 57(12): 1639-1647. (in Chinese)
    [11]
    邢慧堂, 徐前卫, 刘 浩, 等. 盾构近距离上跨既有隧道施工影响及控制研究[J]. 铁道工程学报, 2021, 38(9): 61-67. (XING H T, XU Q W, LIU H, et al. Research on the construction impact and control of shield crossing over existing tunnel at close distance[J]. Journal of Railway Engineering Society, 2021, 38(9): 61-67. (in Chinese)

    XING H T, XU Q W, LIU H, et al. Research on the construction impact and control of shield crossing over existing tunnel at close distance[J]. Journal of Railway Engineering Society, 2021, 38(9): 61-67. (in Chinese)
    [12]
    李兆平, 王 凯, 姜厚停, 等. 长距离叠落盾构隧道施工对已成型隧道影响及控制措施研究[J]. 土木工程学报, 2020, 53(S1): 174-179. (LI Z P, WANG K, JIANG H T, et al. The influence of long distance overlapping shield tunnel construction on the formed tunnel and appropriate countermeasures[J]. China Civil Engineering Journal, 2020, 53(S1): 174-179. (in Chinese)

    LI Z P, WANG K, JIANG H T, et al. The influence of long distance overlapping shield tunnel construction on the formed tunnel and appropriate countermeasures[J]. China Civil Engineering Journal, 2020, 53(S1): 174-179. (in Chinese)
    [13]
    DING Z, ZHANG M B, ZHANG X, et al. Theoretical analysis on the deformation of existing tunnel caused by under-crossing of large-diameter slurry shield considering construction factors[J]. Tunnelling and Underground Space Technology, 2023, 133: 104913. doi: 10.1016/j.tust.2022.104913
    [14]
    赵宇鹏, 陈道政. 盾构隧道上跨施工对既有隧道变形的影响研究[J]. 合肥工业大学学报(自然科学版), 2021, 44(11): 1525-1530. (ZHAO Y P, CHEN Z D. Research on the influence of overcrossing shield tunnel construction on the deformation of existing tunnels[J]. Journal of Hefei University of Technology (Natural Science), 2021, 44(11): 1525-1530. (in Chinese)

    ZHAO Y P, CHEN Z D. Research on the influence of overcrossing shield tunnel construction on the deformation of existing tunnels[J]. Journal of Hefei University of Technology (Natural Science), 2021, 44(11): 1525-1530. (in Chinese)
    [15]
    雷明锋, 石渊博, 唐钱龙, 等. 四洞交叠盾构隧道近距离下穿既有桥梁桩基施工控制技术研究(英文)[J]. Journal of Central South University, 2023, 30(7): 2360-2373. (LEI M F, SHI Y B, TANG Q L, et al. Construction control technology of a four-hole shield tunnel passing through pile foundations of an existing bridge: a case study[J]. Journal of Central South University, 2023, 30(7): 2360-2373. (in Chinese) doi: 10.1007/s11771-023-5368-7

    LEI M F, SHI Y B, TANG Q L, et al. Construction control technology of a four-hole shield tunnel passing through pile foundations of an existing bridge: a case study[J]. Journal of Central South University, 2023, 30(7): 2360-2373. doi: 10.1007/s11771-023-5368-7
    [16]
    李 磊, 张孟喜, 吴惠明, 等. 近距离多线叠交盾构施工对既有隧道变形的影响研究[J]. 岩土工程学报, 2014, 36(6): 1036-1043. (LI L, ZHANG M X, WU H M, et al. Influence of short-distance multi-line overlapped shield tunnelling on deformation of existing tunnels[J]. Chinese Journal of Geotechnical Engineering, 2014, 36(6): 1036-1043. (in Chinese)

    LI L, ZHANG M X, WU H M, et al. Influence of short-distance multi-line overlapped shield tunnelling on deformation of existing tunnels[J]. Chinese Journal of Geotechnical Engineering, 2014, 36(6): 1036-1043. (in Chinese)
    [17]
    李海洋. 四线叠交小间距盾构隧道下穿桥梁沉降控制案例分析[J]. 隧道建设(中英文), 2020, 40(S1): 343-349. (LI H Y. Analys is of settlement control of bridge induced by undercrossing of four-line overlapping small-spacing shield tunnels[J]. Tunnel Construction, 2020, 40(S1): 343-349. (in Chinese)

    LI H Y. Analys is of settlement control of bridge induced by undercrossing of four-line overlapping small-spacing shield tunnels[J]. Tunnel Construction, 2020, 40(S1): 343-349. (in Chinese)
    [18]
    李召峰, 李术才, 刘人太, 等. 富水破碎岩体注浆加固实验与机制研究[J]. 岩石力学与工程学报, 2017, 36(1): 198-207. (LI Z F, LI S C, LIU R T, et al. Grouting reinforcement experiment for water-rich broken rock mass[J]. Chinese Journal of Rock Mechanics and Engineering, 2017, 36(1): 198-207. (in Chinese)

    LI Z F, LI S C, LIU R T, et al. Grouting reinforcement experiment for water-rich broken rock mass[J]. Chinese Journal of Rock Mechanics and Engineering, 2017, 36(1): 198-207. (in Chinese)
    [19]
    SANG H M, LIU B, LIU Q S, et al. Study of grouting reinforcement mechanism in fractured rock mass and its engineering application[J]. International Journal of Geomechanics, 2024, 24(5): 04024057. doi: 10.1061/IJGNAI.GMENG-9366
    [20]
    中华人民共和国住房和城乡建设部. 城市轨道交通工程监测技术规范: GB 50911—2013[S]. 北京: 中国建筑工业出版社, 2013. (Ministry of Housing and Urban-Rural Development of the People’s Republic of China. Code for monitoring measurement of urban rail transit engineering: GB 50911—2013[S]. Beijing: China Architecture & Building Press, 2013. (in Chinese)

    Ministry of Housing and Urban-Rural Development of the People’s Republic of China. Code for monitoring measurement of urban rail transit engineering: GB 50911—2013[S]. Beijing: China Architecture & Building Press, 2013. (in Chinese)
    [21]
    肖明清, 封 坤, 周子扬, 等. 盾构隧道施工期管片错台影响因素研究[J]. 岩土工程学报, 2023, 45(7): 1347-1356. (XIAO M Q, FENG K, ZHOU Z Y, et al. Study on the influencing factors for segment dislocation during shield tunnelling[J]. Chinese Journal of Geotechnical Engineering, 2023, 45(7): 1347-1356. (in Chinese)

    XIAO M Q, FENG K, ZHOU Z Y, et al. Study on the influencing factors for segment dislocation during shield tunnelling[J]. Chinese Journal of Geotechnical Engineering, 2023, 45(7): 1347-1356. (in Chinese)
    [22]
    夏曾银, 潘 军, 盛鲁腾, 等. 注浆和隔离墙对基坑引发隧道变形的联合控制作用研究[J]. 水利水电技术(中英文), 2022, 53(9): 175-185. (XIA Z Y, PAN J, SHENG L T, et al. Study on joint control effect of grouting and separating wall on tunnel deformation induced by foundation pit[J]. Water Resources and Hydropower Engineering, 2022, 53(9): 175-185. (in Chinese)

    XIA Z Y, PAN J, SHENG L T, et al. Study on joint control effect of grouting and separating wall on tunnel deformation induced by foundation pit[J]. Water Resources and Hydropower Engineering, 2022, 53(9): 175-185. (in Chinese)
    [23]
    张伟杰. 隧道工程富水断层破碎带注浆加固机理及应用研究[D]. 济南: 山东大学, 2014. (ZHANG W J. Mechanism of grouting reinforcement of water-rich fault fractured zone and its application in tunnel engineering[D]. Ji’nan: Shandong University, 2014. (in Chinese)

    ZHANG W J. Mechanism of grouting reinforcement of water-rich fault fractured zone and its application in tunnel engineering[D]. Ji’nan: Shandong University, 2014. (in Chinese)
    [24]
    中华人民共和国水利部. 水利水电工程注水试验规程: SL 345—2007[S]. 北京: 中国水利水电出版社, 2008. (Ministry of Water Resources of the People’s Republic of China. Code of water injection test for water resources and hydropower engineering: SL 345—2007[S]. Beijing: China Water Conservancy and Hydropower Press, 2008. (in Chinese)

    Ministry of Water Resources of the People’s Republic of China. Code of water injection test for water resources and hydropower engineering: SL 345—2007[S]. Beijing: China Water Conservancy and Hydropower Press, 2008. (in Chinese)
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Figures(9)  / Tables(6)

    Article Metrics

    Article views (19) PDF downloads(1) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return